The first drone shot of the new fence around the pool complex.  With no chance of rain Tuesday - Thursday of this week they will be spraying the plaster on the inside of the pool.  Immediately following the plaster they will start filling the pools with water.  More deck concrete this week and north pool house sidewalks.  


A view south of the pool to 9 green.  Topsoil will be spread back around on Monday and irrigation installation starts on Wednesday in this area.

Here is a view of both facilities under construction.

Water and ice will be available for refills at the turn.
A late Friday planning meeting for this week's start of the 1st tee and putting green complex.  Irrigation reroute for 18 green Tuesday morning then bulldozer shaping on Wednesday.

We finished adding the green bank sod on the west side of 9 along the cart path and we also softened the slope on the west side of the cart path.  This week we will be seeding along the cart path and around the back tee.  