Wednesday, October 2, 2019

September Progress and into October


Lots of progress during September in and around the 1st tee complex.


Here is a picture of the many different paint color options that the committee reviewed for the new fitness center walls, ceiling and the very grand exposed beams.

Starting off the first week of October with a bang!  My crew is  sodding the putting green bank.  The collar of the putting green sod transferred well from behind 9 green and we have seed germination on the putting green!

On the left is the new first tee.  We have been using it for special events and weekends when the construction crew isn't working on site.

A view from inside the new golf shop, carpet and paint are next.

In early September we had the entrance woods hydroseeded and grass is now growing. 

A close version of the brick pavers that will be outside the lower level which starts the week of October 7th.

Removing the old blacktop.

Installing new drainage.

Seeding the new putting green.
I launched the drone one day last week to get some 1 tee progress  pictures and captured this great one on #9.